Report 19 of the 23 Oct 03 meeting of the Finance Committee and sets out details of the negotiated costs to extend the existing Direct Labour Services contract until 31 December 2005.

Warning: This is archived material and may be out of date. The Metropolitan Police Authority has been replaced by the Mayor's Office for Policing and Crime (MOPC).

See the MOPC website for further information.

Property services outsource contracts and commercial strategy beyond their initial expiry date of 1 January 2004

Report: 19
Date: 23 October 2003
By: Commissioner

Summary

This report sets out details of the negotiated costs to extend the existing Direct Labour Services contract until 31 December 2005.

A. Recommendation

Members are asked to agree the recommendations in the linked exempt report.

B. Supporting information

1. On 10 April 2003 members of the Finance Committee endorsed proposals to enter into negotiations with the present Direct Labour Services contractor to:

  1. extend the term of their contract by a further two years to 31 December 2005 as permitted within the conditions of their contract.
  2. extend the scope of their contract for the period 1 January 2004 to 31 December 2005.
  3. to appoint consultants to negotiate and draw up revised contractual terms on behalf of the MPA.

C. Equality and diversity implications

The trade unions have been kept fully informed as negotiations have proceeded.

D. Financial implications

The financial implications are detailed in the linked exempt report.

E. Background papers

F. Contact details

Report author: Alan Croney, Director of Property Services, MPS.